Terra Construction Update Sep 2018

FRONT ELEVATION
TOWER – 20 • 90% EXTERNAL PLASTER WORKS COMPLETED • 100% INTERNAL PLASTER WORKS COMPLETED • 56/76 UNITS IPS FLOORING WORKS COMPLETED • TILE/STONE WORKS IN PROGRESS
TOWER – 21 • 90% EXTERNAL PLASTER WORKS COMPLETED • 100% INTERNAL PLASTER WORKS COMPLETED
TOWER – 22 • 19TH FLOOR SLAB CASTED • 2 ND TO 17TH FLOOR BRICK WORKS COMPLETED • 2 ND TO 15TH FLOOR INTERNAL PLASTER WORKS COMPLETED REST IN PROGRESS
TOWER – 23 • 19TH FLOOR SLAB CASTED • 2 ND TO 17TH FLOOR BRICK WORKS COMPLETED • 2 ND TO 8 TH FLOOR INTERNAL PLASTER WORKS COMPLETED REST IN PROGRESS
TOWER – 24 • 85% EXTERNAL PLASTER WORKS COMPLETED • 100% INTERNAL PLASTER WORKS COMPLETED
TOWER – 25 • 85% EXTERNAL PLASTER WORKS COMPLETED • 100% INTERNAL PLASTER WORKS • 24/76 UNITS IPS FLOORING WORKS COMPLETED
TOWER 22 BRICK WORKS IN PROGRESS
TOWER 23 DOOR FRAME FIXING WORKS IN PROGRESS
TOWER 22 PLASTER WORKS IN PROGRESS
TOWER 23 PLASTER WORKS IN PROGRESS
TOWER 20 IPS FLOORING WORKS IN PROGRESS
COL. SHUTT. AT BASEMENT LVL.