Slideshow Image 1

Visionnaire Villas Construction Update Sep 2018

MAIN ENTRANCE – FINISHING WORKS IN PROGRESS
A-19 TO A-21 EXTERNAL PLASTER AND BLOCK WORKS IN PROGRESS
B-87 TO B-91 BLOCK WORKS IN PROGRESS
B-87 TO B-91 BLOCK WORKS IN PROGRESS
B-161 TO B-167 RCC & BLOCK WORKS IN PROGRESS
B-161 TO B-185 RCC & BLOCK WORKS IN PROGRESS
B-168 TO B-185 RCC & BLOCK WORKS IN PROGRESS
B-189 TO B-199 EXTERNAL PLASTER AND BLOCK WORKS IN PROGRESS
PARK NO 04 PATHWAY AND STONE FIXING WORKS IN PROGRESS
33 KV SUBSTATION MS AND BRICK WORKS IN PROGRESS