Discovery Park Construction Update April 2018

TOWER - K • GROUND TO 15TH FLOOR INTERNAL PLASTER COMPLETED • 52/56 FLATS DADO WORKS COMPLETED, 52/56 FLATS TOILET FLOORING WORKS COMPLETED AND 50/56 D&D TILING WORKS COMPLETED • 150/168 NOS. BALCONY CILL STONE WORKS COMPLETED • 52/56 FLATS KITCH
TOWER - J • 228/258 RAILING WORKS COMPLETED • 1 ST TO 15TH FLOOR INTERNAL PLASTER WORKS COMPLETED. • 82/86 FLATS IPS FLOORING COMPLETED • 70/86 FLATS DADO WORKS COMPLETED, 70/86 FLATS TOILET FLOORING WORKS COMPLETED AND 70/86 D&D TILING WORKS CO
TOWER - H • 300/300 RAILING WORKS COMPLETED • GROUND TO 15TH FLOOR INTERNAL PLASTER WORKS COMPLETED • 86/90 FLATS IPS FLOORING COMPLETED • 78/90 FLATS DADO WORKS COMPLETED, 72/90 FLATS TOILET FLOORING WORKS COMPLETED AND 78/90 D&D TILING WORKS CO
TOWER - G • 320/330 RAILING WORKS COMPLETED • GROUND TO 15TH FLOOR INTERNAL PLASTER WORKS COMPLETED • 66/90 FLATS DADO WORKS COMPLETED • 60/90 FLATS TOILET FLOORING WORKS COMPLETED • 66/90 D&D TILING WORKS COMPLETED • 300/330 NOS. BALCONY CIL
TOWER - F • 300/300 RAILING WORKS COMPLETED • GROUND TO 15TH FLOOR INTERNAL PLASTER WORKS COMPLETED • 78/90 FLATS DADO WORKS COMPLETED • 78/90 FLATS TOILET FLOORING WORKS COMPLETED • 78/90 D&D TILING WORKS COMPLETED • 240/300 NOS. BALCONY CIL
TOWER - L 8 TH FLOOR SLAB WORKS COMPLETED. 1 ST TO 4TH FLOOR BRICK WORKS COMPLETED.
TOWER - M 11TH FLOOR SLAB CASTED. 1 ST TO 5TH FLOOR BRICK WORKS COMPLETED.
TOWER - A • TERRACE SLAB CASTED. • GROUND TO 14TH FLOOR BRICK WORKS COMPLETE • 75/88 FLATS INTERNAL PLASTER WORKS COMPLETED • 80% EXTERNAL PLASTER WORKS COMPLETED • 22/88 FLATS IPS FLOORING WORKS COMPLETED • RAILING FIXING WORKS IN PROGRESS.
TOWER - B • 18TH FLOOR LEVEL SLAB COMPLETED • 1 ST TO 15TH FLOOR BRICK WORKS COMPLETE • 92/142 FLATS INTERNAL PLASTER WORKS COMPLETED • 30% EXTERNAL PLASTER WORKS COMPLETED • 22/88 FLATS IPS FLOORING WORKS COMPLETED • RAILING FIXING WORKS IN
CLUB STRUCTURE WORKS IN PROGRESS
WATERBODY WORKS IN PROGRESS AT MAIN ENTRANCE
LANDSCAPING WORKS IN PROGRESS
LANDSCAPING WORKS IN PROGRESS
LANDSCAPING WORKS IN PROGRESS
LANDSCAPING WORKS IN PROGRESS
LANDSCAPING WORKS IN PROGRESS NEAR TOWER F, G & H
TOWER - H SAMPLE FLAT
TOWER - H SAMPLE FLAT
TOWER - H SAMPLE FLAT
TOWER - H SAMPLE FLAT