Discovery Park Construction Update Aug 2017

TOWER A - • 14TH FLOOR LEVEL SLAB CASTED. • 15TH FLOOR LEVEL SLAB WORKS IN PROGRESS. • GROUND TO 9TH FLOOR BRICKWORKS COMPLETED. • 10TH FLOOR BRICKWORKS IN PROGRESS. • 18/88 FLATS INTERNAL PLASTER COMPLETED.
TOWER B - • 12TH FLOOR LEVEL SLAB COMPLETED. • 14TH FLOOR LEVEL SLAB WORKS IN PROGRESS. • 1ST TO 8TH FLOOR BRICKWORKS COMPLETED. • 8/142 FLATS INTERNAL PLASTER WORKS COMPLETED.
TOWER F - • BRICKWORKS COMPLETED. • 250/300 RAILING WORKS IS COMPLETED. • ALL FLATS INTERNAL PLASTER COMPLETED. • SOME LOBBY AREA INTERNAL PLASTER WORKS IN PROGRESS. • 70% EXTERNAL PLASTER WORKS COMPLETED • 18/90 FLATS IPS FLOORING WORKS COMPL
TOWER G - • BRICKWORKS COMPLETED. • 215/330 RAILING WORKS IS COMPLETED. • ALL FLATS INTERNAL PLASTER COMPLETED. • SOME LOBBY AREA INTERNAL PLASTER WORKS IN PROGRESS. • 50% EXTERNAL PLASTER WORKS COMPLETED • 24/90 FLATS IPS FLOORING WORKS COMPL
TOWER H - • BRICKWORKS COMPLETED. • 150/300 RAILING WORKS IS COMPLETED, REST IN PROGRESS. • GROUND TO 11TH FLOOR INTERNAL PLASTER COMPLETED. • 55% EXTERNAL PLASTER WORKS COMPLETED • 36/90 FLATS IPS FLOORING WORKS COMPLETED. • STAIRCASE KOTA ST
TOWER J - • BRICKWORKS COMPLETED. • 228/258 RAILING WORKS IS COMPLETED, REST IN PROGRESS. • 2 FLATS ON GROUND FLOOR, 1ST, 4TH TO 11TH FLOOR INTERNAL PLASTER COMPLETED. • 50% EXTERNAL PLASTER WORKS COMPLETED • 12/86 FLATS IPS FLOORING WORKS COMPL
TOWER K - • 168/168 RAILING WORKS COMPLETED • INTERNAL PLASTER COMPLETED FOR 1ST, 4TH TO 6TH, 3 FLATS ON 7TH, 3 FLATS ON 8TH, 9TH TO 15TH FLOOR. • 60% EXTERNAL PLASTER WORKS COMPLETED • IPS WORKS COMPLETED FOR 3 FLATS ON 1ST, 4TH TO 6TH, 3 FLATS O
TOWER L - • 2ND FLOOR LEVEL SLAB CASTING WORKS IN PROGRESS.
TOWER M - • 07TH FLOOR LEVEL SLAB WORKS IN PROGRESS. • 1ST & 2ND FLOOR BRICKWORKS IN PROGRESS.