Discovery Park Construction Update June 2017

TOWER A - 12TH FLOOR LEVEL SLAB CASTED. • 12TH TO 14TH FLOOR COLUMN CASTING WORKS IN PROGRESS. • GROUND TO 3RD FLOOR AND 5TH TO 8TH FLOOR BRICKWORKS COMPLETED. • 4 TH FLOOR BRICKWORKS IN PROGRESS. • INTERNAL PLASTER COMPLETED FOR 5 FLATS.
TOWER B - 10TH FLOOR LEVEL SLAB CASTED. • 11TH TO 12TH FLOOR COLUMN CASTING WORKS IN PROGRESS. • 1 ST TO 7TH FLOOR BRICKWORKS COMPLETED. • 8 TH FLOOR BRICKWORKS IN PROGRESS.
TOWER F - BRICKWORKS COMPLETED. • 150/300 RAILING WORKS IS COMPLETED • 11TH & 12TH FLOOR PLASTER WORKS IN PROGRESS. • 25% EXTERNAL PLASTER WORKS COMPLETED • 7 TH FLOOR INTERNAL PUTTY WORKS IN PROGRESS
TOWER G - BRICKWORKS COMPLETED. • 100/330 RAILING WORKS COMPLETED • GROUND TO 9TH FLOOR, 12TH FLOOR INTERNAL PLASTER WORKS COMPLETED. • 10TH &11TH FLOOR INTERNAL PLASTER WORKS IN PROGRESS. • 25% EXTERNAL PLASTER WORKS COMPLETED • 08 FLAT IPS WOR
TOWER H - BRICKWORKS COMPLETED. • 150/300 RAILING WORKS COMPLETED • GROUND TO 9TH FLOOR INTERNAL PLASTER WORKS COMPLETED. • 10TH & 11TH FLOOR INTERNAL PLASTER WORKS IN PROGRESS. • 15 FLAT IPS WORKS COMPLETED • STAIRCASE KOTA STONE WORKS IN PROGR
TOWER J - BRICKWORKS COMPLETED. • 100/258 RAILING WORKS COMPLETED • INTERNAL PLASTER WORKS COMPLETED FOR 1ST & 4TH TO 11TH FLOOR AND 2 FLATS ON GF. • 20% EXTERNAL PLASTER WORKS COMPLETED • 44/258 BALCONY CILL STONE WORKS COMPLETED
TOWER K - BRICKWORKS COMPLETED. • 125/168 RAILING WORKS COMPLETED • INTERNAL PLASTER COMPLETED FOR 1 ST, 4TH TO 6TH, 2 FLATS ON 7TH, 2 FLATS ON 8TH, 9TH TO 14TH FLOOR. • 60% EXTERNAL PLASTER WORKS COMPLETED • IPS WORKS COMPLETED FOR 3 FLATS ON 1ST
TOWER L - 1 ST FLOOR LEVEL SLAB CASTING WORKS IN PROGRESS.
TOWER M - 06TH FLOOR LEVEL SLAB WORKS IN PROGRESS. • 1 ST FLOOR BRICKWORKS IN PROGRESS.