Discovery Park Construction Update June 2018

TOWER - K • 56/56 FLATS DADO WORKS COMPLETED, 56/56 FLATS TOILET FLOORING WORKS COMPLETED AND 56/56 D&D TILING WORKS COMPLETED • 168/168 NOS. BALCONY CILL STONE WORKS COMPLETED • 56/56 FLATS KITCHEN COUNTER STONE WORKS COMPLETED • 95% STAIRCASE KOTA STONE WORKS COMPLETED • 56/56 FLATS INTERNAL PUTTY WORKS COMPLETED • 100% EXTERNAL PUTTY WORKS COMPLETED • 56/56 FLATS DOOR SHUTTER WORKS COMPLETED • 56/56 FLATS UPVC DOOR & WINDOWS WORKS COMPLETED
TOWER - J • 258/258 RAILING WORKS COMPLETED • GROUND TO 15TH FLOOR INTERNAL PLASTER WORKS COMPLETED. • 86/86 FLATS IPS FLOORING COMPLETED • 84/86 FLATS DADO WORKS COMPLETED, 84/86 FLATS TOILET FLOORING WORKS COMPLETED AND 84/86 D&D TILING WORKS COMPLETED • 258/258 NOS. BALCONY CILL STONE WORKS COMPLETED • 86/86 FLATS KITCHEN COUNTER STONE WORKS COMPLETED • 95% STAIRCASE KOTA STONE WORKS COMPLETED • 100% EXTERNAL PUTTY WORKS COMPLETED • 66/86 FLATS DOOR SHUTTER WORKS COMPLETED • 95% UPVC DOOR & WINDOWS WORKS COMPLETED • 80/86 FLATS INTERNAL WIRING WORKS COMPLETED
TOWER - H • 90/90 FLATS IPS FLOORING COMPLETED • 90/90 FLATS DADO WORKS COMPLETED, 90/90 FLATS TOILET FLOORING WORKS COMPLETED AND 90/90 D&D TILING WORKS COMPLETED • 300/300 NOS. BALCONY CILL STONE WORKS COMPLETED • 90/90 FLATS KITCHEN COUNTER STONE WORKS COMPLETED • 95% STAIRCASE KOTA STONE WORKS COMPLETED • 90/90 FLATS DOOR SHUTTER WORKS COMPLETED • 95% UPVC DOOR & WINDOWS WORKS COMPLETED • 67/90 FLATS WIRING WORKS COMPLETED • LIFT CAR INSTALLED
TOWER - G • 330/330 RAILING WORKS COMPLETED • 90/90 FLATS DADO WORKS COMPLETED • 90/90 FLATS TOILET FLOORING WORKS COMPLETED • 90/90 D&D TILING WORKS COMPLETED • 330/330 NOS. BALCONY CILL STONE WORKS COMPLETED • 84/90 FLATS KITCHEN COUNTER STONE WORKS COMPLETED • 95% STAIRCASE KOTA STONE WORKS COMPLETED • 90/90 FLATS INTERNAL PUTTY WORKS COMPLETED • 95% EXTERNAL PUTTY WORKS COMPLETED • 88/90 FLATS DOOR SHUTTER WORKS COMPLETED • 95% UPVC DOOR & WINDOWS WORKS COMPLETED • 86/90 FLATS WIRING WORKS IN PROGRESS • LIFT CAR INSTALLED & TESTING IN PROGRESS
TOWER - F • 90/90 FLATS DADO WORKS COMPLETED • 90/90 FLATS TOILET FLOORING WORKS COMPLETED • 90/90 D&D TILING WORKS COMPLETED • 300/300 NOS. BALCONY CILL STONE WORKS COMPLETED • 90/90 FLATS KITCHEN COUNTER STONE WORKS COMPLETED • 100% STAIRCASE KOTA STONE WORKS COMPLETED • 90/90 FLATS DOOR SHUTTER WORKS COMPLETED • 90% UPVC DOOR & WINDOWS WORKS COMPLETED • 72/90 FLATS WIRING WORKS IN PROGRESS
TOWER - L 10TH FLOOR SLAB WORKS COMPLETED. 1 ST TO 4TH FLOOR BRICK WORKS COMPLETED.
TOWER - M 12TH FLOOR SLAB CASTED. 1 ST TO 5TH FLOOR BRICK WORKS COMPLETED.
TOWER - A • TERRACE SLAB CASTED • GROUND TO 14TH FLOOR BRICK WORKS COMPLETE • 75/88 FLATS INTERNAL PLASTER WORKS COMPLETED • 80% EXTERNAL PLASTER WORKS COMPLETED • 24/88 FLATS IPS FLOORING WORKS COMPLETED • RAILING FIXING WORKS IN PROGRESS
TOWER - B • 18TH FLOOR LEVEL SLAB COMPLETED • 1 ST TO 15TH FLOOR BRICK WORKS COMPLETE • 92/142 FLATS INTERNAL PLASTER WORKS COMPLETED • 35% EXTERNAL PLASTER WORKS COMPLETED • RAILING FIXING WORKS IN PROGRESS.
CLUB STRUCTURE WORKS IN PROGRESS
MAIN ENTRANCE WORKS IN PROGRESS
LANDSCAPING WORKS IN PROGRESS
WATERBODY WORKS IN PROGRESS