TOWER A - 15TH FLOOR SLAB CASTED. • 15TH TO TERRACE COLUME CASTING WORKS IN PROGRESS. • GROUND TO 12TH FLOOR BRICKWORKS COMPLETED. • 34/88 FLATS INTERNAL PLASTER WORKS COMPLETED.
TOWER B - 14TH FLOOR SLAB COMPLETED. • 15TH FLOOR SLAB WORKS IN PROGRESS. • 1ST TO 10TH FLOOR BRICKWORKS COMPLETED. • 11TH FLOOR BRICKWORKS IN PROGRESS. • 38/142 FLATS INTERNAL PLASTER WORKS COMPLETED.
TOWER F - 92% EXTERNAL PLASTER WORKS COMPLETED • 42/90 FLATS IPS FLOORING WORKS COMPLETED. • TOILET DADO-18/90 FLATS, TOILET FLOOR-18/90 FLATS, D&D-5/90 FLATS TILLING WORKS COMPLETED • BALCONY CILL-55/300 NOS., KITCHEN COUNTER- 42/90 FLATS STONE WOR
TOWER G - 215/330 RAILING WORKS IS COMPLETED. • GROUND – 15th INTERNAL PLASTER COMPLETED. • 80% EXTERNAL PLASTER WORKS COMPLETED • 84/90 FLATS IPS FLOORING WORKS COMPLETED. • 10/90 FLATS TOILET DADO, 6/90 TOILET FLOOR, 9/90 D&D TILING WORKS COMP
TOWER H - 230/300 RAILING WORKS IS COMPLETED, REST IN PROGRESS. • GROUND TO 15TH FLOOR INTERNAL PLASTER COMPLETED. • 70% EXTERNAL PLASTER WORKS COMPLETED • 84/90 FLATS IPS FLOORING WORKS COMPLETED. • 51/90 FLATS - TOILET DADO, 45/90 TOILET FLOOR,
TOWER J - 228/258 RAILING WORKS IS COMPLETED, REST IN PROGRESS. • 2 FLATS ON GROUND FLOOR, 1ST, 4TH TO 11TH FLOOR INTERNAL PLASTER COMPLETED. • 60% EXTERNAL PLASTER WORKS COMPLETED • 22/86 FLATS IPS FLOORING WORKS COMPLETED. • 06/86 FLATS TOILET D
TOWER K - 1ST TO 15TH FLOOR INTERNAL PLASTER WORKS COMPLETED. REST IS IN PROGRESS. • 95% EXTERNAL PLASTER WORKS COMPLETED • 47/56 FLATS IPS WORKS COMPLETED • 30/86 FLATS TOILET DADO, 6/86 FLATS TOILET FLOOR, 1/86 FLATS D&D TILLING WORKS COMPLETED.
TOWER L - 4TH FLOOR SLAB CASTING WORKS IN PROGRESS.
TOWER M - 08TH FLOOR SLAB WORKS IN PROGRESS. • 3RD FLOOR BRICKWORKS IN PROGRESS.