AQ2 - 01 TO 08 GRADE SLAB, STONE & TILE FIXING, BRICK BAT COBA WORKS IN PROGRESS
81 AVE - 35 TO 42 EXTERNAL & INTERNAL PLASTER, DOOR FRAME FIXING WORKS IN PROGRESS
81 AVE - 63 & 64 TILING WORKS IN PROGRESS
AQ5 - 14 TO 21 EXTERNAL PLASTER, WATER TANK BRICKWORK, IPS FLOORING WORKS IN PROGRESS
AQ5 - 22 TO 29 INTERNAL PLASTER, GRADE SLAB, IPS, R.C.C WATER TANK, BRICK BAT COBA WORKS IN PROGRESS
AQ5 - 06 TO 12A EXTERNAL & INTERNAL PLASTER WORKS IN PROGRESS
CL3 - 07 TO 12 EXTERNAL & INTRNAL PLASTER, IPS FLOORING, BRICK BAT COBA WORKS IN PROGRESS
CL4 - 07 TO 12 STONE & TILE WORKS IN PROGRESS
CL8 - 04 TO 06A TILE FIXING, INTERNAL PAINTING WORKS IN PROGRESS
PAVER WORKS IN PROGRESS
OMEGA 12 - 01 TO 06 BOUNDARY WALL BRICK WORKS IN PROGRESS
OMEGA 28 - 02 TO 10 INTERNAL PLASTER, IPS FLOORING, GRADE SLAB WORKS IN PROGRESS
VL1 - 12 TO 20 BRICK WORKS IN PROGRESS
VL1 - 11 TO 19 BRICK WORKS IN PROGRESS