Park Elite Floors I and II Construction Update Feb 2017

E Block

E32-09 TO E32-19 BLOCK-E-115
E-22 BLOCK BRICK & SHUTTERING WORKS IN PROGRESS
E32-02 TO E32-07 (BLOCK E-115)
E-85 BLOCK PLASTER WORKS IN PROGRESS
E40-01 TO E40-23 (E-85-BLOCK)
E-85 BLOCK BEDROOM IPS WORKS IN PROGRESS
E-85 BLOCK TILE WORKS IN PROGRESS
E-85 TILE WORKS IN PROGRESS
E-115 BLOCK EXTERNAL PAINTING WORKS IN PROGRESS
E-115 BLOCK INTERNAL PAINTIN WORKS IN PROGRESS
E-115 BLOCKINTERNAL PAINTING WORKS IN PROGRESS

H Block

H-34 TO H-41 (H-BLOCK)
H-34 TO H-41
H-79 BLOCK PAINTING WORKS IN PROGRESS
H-79 PARKING AREA WORKS IN PROGRESS

L Block

L15-14 TO L15-23 (L-37 BLOCK)
LM-BLOCK LM4-38 TO LM-58
LM4-38 TO 58 EXTERNAL PLASTER WORK IN PROGRESS
L15 - 14 TO 18 INTERNAL PAINTING WORKS IN PROGRESS

M Block

M11-10 to M11-20
M11-10A TO 20 INTERNAL FINISHING WORKS IN PROGRESS
M11-1 TO 9 INTERNAL TILE FLOORING WORKS IN PROGRESS

P Block

P - BLOCK
P - BLOCK
P - BLOCK
P - BLOCK
P - BLOCK
P - BLOCK
P - BLOCK
P - BLOCK
P4-34 TERRACE PLASTER WORKS IN PROGRESS
P4-46 FF TILE WORKS IN PROGRESS
P-BLOCK EXTERNAL PLASTER WORKS IN PROGRESS
P-BLOCK EXTERNAL WORKS IN PROGRESS
PE-26 TP PE-29
PE-108 TO PE-116
PE-115 BRICK WORKS IN PROGRESS
PC-77 TO PC-85
PC-77 TO PC-93 ROW
PC-93