Park Elite Floors I and II Construction Update July 2017

E Block

E-115 BLOCK EXTERNAL PAINTING WORKS IN PROGRESS
E-85 BLOCK EXTERNAL PLASTER WORKS IN PROGRESS
E-85 BLOCK KOTA GRANDING WORKS IN PROGRESS
E-115 BLOCK INTERNAL PAINTING WORKS IN PROGRESS
E-115 BLOCK TILES WORKS IN PROGRESS

H Block

BLOCK-H EXTERNAL PAINTING WORKS IN PROGRESS
H-BLOCK EXTERNAL PLASTER WORKS IN PROGRESS

L Block

BLOCK-L15 (14 to 23)
L15-14 TO 18 ELECTRICAL WIRING WORKS IN PROGRESS
L15-02 TO 11 KOTA STONE FIXING WORKS IN PROGRESS

LM Block

LM4 (38 to 58)
MANHOLE BRICK WORKS IN PROGRESS
LM4-49 TO 61 PLUMBING WORKS IN PROGRESS

M Block

BLOCK M11 (01 TO 09) EXTERNAL PAINTING WORKS IN PROGRESS
BLOCK M11-01 TO 09 INTERNAL PAINTING WORKS IN PROGRESS

P Block

P-BLOCK P4-02 TO P4-60 EXTERNAL PLASTER , EXTERNAL PAINTING, INTERNAL FLOORING & WORKS IN PROGRESS
BLOCK P4-56 & P4-54 EXTERNAL PAINTING WORKS IN PROGRESS
BLOCK P4-16 & P4-18 EXTERNAL PLASTER & PAINTING WORKS IN PROGRESS
BLOCK P4-24 & 26 EXTERNAL PLASTER & PAINTING WORKS IN PROGRESS
BLOCK P8-02 & P8-04 EXTERNAL PLASTER WORKS IN PROGRESS
BLOCK P4-20 BOUNDARY WALL EXTENAL PLASTER WORKS IN PROGRESS
BLOCK P4-32 EXTERNAL PLASTER WORKS IN PROGRESS

PA Block

PA-240 TO 241 EXTERNAL PLASTER WORKS IN PROGRESS
PA-241 TO 237 PARAPET PLASTER WORKS IN PROGRESS
PA-241 TO PA-236 SHAFT PLASTER WORKS IN PROGRESS
PA-242 TO 247 BOUNDARY WALL BRICK WORKS IN PROGRESS

PC Block

PC-37 TO 53 EXTERNAL PLASTER WORKS IN PROGRESS
PC-67 TO 76 INTERNAL DRAINAGE AND EXTERNAL DRAINAGE WORKS IN PROGRESS
PC-72 TO 76 INTERNAL PLUMBING WORKS IN PROGRESS
PC-76 TO 67 EXTERNAL DRAINAGE CONNECTION WORKS IN PROGRESS
PC-77 TO 78 INTERNAL DOOR SHUTTER FIXING WORKS IN PROGRESS
PC-77 TO 81 INTERNAL PUTTY WORKS IN PROGRESS
PC-83 TO 84 STAIRCASE KOTA FIXING WORKS IN PROGRESS
PC-85 TO 86 TILING WORKS IN PROGRESS
PC-87 TO 93 IPS FLOORING WORKS IN PROGRESS
PC-238 TO 241 BACK SIDE VERANDAH BRICK WORKS IN PROGRESS