Park Elite Floors I and II Construction Update Oct 2017

E Block

BLOCK -E-85 INTERNAL FINISHING WORKS IN PROGRESS
BLOCK E-85 EXTERNAL PAINTING WORKS IN PROGRESS
BLOCK E-85 EXTERNAL PLASTER WORKS IN PROGRESS
BLOCK E-115 EXTERNAL PLASTER & INTERNAL FINISHING WORKS IN PROGRESS
BLOCK E-115 EXTERNAL PLASTER AND INTERNAL FINISHING WORKS IN PROGRESS
BLOCK E-17 EXTERNAL PLASTER WORKS IN PROGRESS
BLOCK E-85 EXTERNAL BOUNDARY WALL WORKS IN PROGRESS

H Block

BLOCK H-79 EXTERNAL PAINTING WORKS IN PROGRESS

L Block

BLOCK L-15 (2 to 11) EXTERNAL PLASTER WORKS IN PROGRESS
BLOCK L-15 (2 to 11) INTERNAL PAINTING WORKS IN PROGRESS
BLOCK L-15 (2 to 11) KOTA GRANDING WORKS IN PROGRESS
BLOCK L-15 (2 to 11) KOTA STONE FIXING WORKS IN PROGRESS
BLOCK L-15 (2 to 11) PLUMBING MAN HOLE FIXING WORKS IN PROGRESS

LM Block

BLOCK LM 4 - (49 to 61)
BLOCK LM 4 (38 to 58)
BLOCK LM 4 (38 TO 58) INTERNAL PLASTER WORKS IN PROGRESS

P Block

BLOCK - P EXTERNAL PAINTING & INTERNAL FINISHING WORKS IN PROGRESS
BLOCK - P EXTERNAL PAINTING WORKS IN PROGRESS
BLOCK - P EXTERNAL PLASTER & EXTERNAL PAINTING WORKS IN PROGRESS
BLOCK – P EXTERNAL PLASTER WORKS IN PROGRESS
BLOCK – P EXTERNAL PLASTER WORKS IN PROGRESS
BLOCK – P INTERNAL FINISHING WORKS IN PROGRESS
BLOCK – P INTERNAL PAINTING WORKS IN PROGRESS

PA Block

BLOCK - PA-228 TO 241 EXTERNAL PLASTER WORKS IN PROGRESS

PC Block

BLOCK - PC-77 TO 93 EXTERNAL & INTERNAL PAINTING, OVERHEAD TANK FIXING AND FLOORING WORKS IN PROGRESS
BLOCK – PC - 37 TO 53 INTERNAL PLUMBING WORKS IN PROGRESS
BLOCK – PC - 60 TO 76 IPS FLOORING & INTERNAL PLUMBING TESTING WORKS IN PROGRESS
BLOCK – PC-76 TO 60 INTERNAL AND EXTERNAL PLUMBING WORKS IN PROGRESS
BLOCK – PC-76 TO 90 STAIRCASE RAILLING WORKS IN PROGRESS
BLOCK – PC-37 TO 40 INTERNAL PLUMBING WORKS IN PROGRESS
BLOCK – PC-77 TO 86 FLOOR AND WALL TILES WORKS COMPLETED
BLOCK – PC-87 BALCONY TILE FIXING WORKS IN PROGRESS

PE Block

BLOCK - PE EARTH WORKS IN PROGRESS
BLOCK - PE EXTERNAL PLASTER WORKS IN PROGRESS
BLOCK - PE EXTERNAL PLASTER WORKS IN PROGRESS
BLOCK - PE EXTERNAL PLASTER WORKS IN PROGRESS
BLOCK - PE EXTERNAL PLASTER WORKS IN PROGRESS
BLOCK - PE FLOORING WORKS IN PROGRESS
BLOCK - PE BRICK WORKS IN PROGRESS
BLOCK - PE BRICK WORKS IN PROGRESS
BLOCK - PE INTERNAL BRICK WORKS IN PROGRESS
BLOCK - PE IPS FLOORING WORKS IN PROGRESS
BLOCK - PE KOTA FLOORING WORKS IN PROGRESS