Park Elite Premium Construction Update Nov 2017

TOWER L
TOWER M
TOWER N
TOWER H
TOWER J - 95% STONE/TILING WORKS COMPLETED • 90% INTERNAL PUTTY/PAINTING WORKS COMPLETED • 90% INTERNAL WIRING WORKS COMPLETED
TOWER K - 95% STONE/TILING WORKS COMPLETED • 90% INTERNAL PUTTY/PAINTING WORKS COMPLETED • 90% INTERNAL WIRING WORKS COMPLETED
TOWER A - 98% INTERNAL PLASTER WORKS COMPLETED • 9 UNITS IPS FLOORING WORKS IS BALANCE • 70% EXTERNAL STORM, SEWERAGE & WATER SUPPLY WORKS COMPLETED
TOWER B - 99% BRICK WORKS COMPLETED • 98% INTERNAL PLASTER WORKS COMPLETED • 95% EXTERNAL PLASTER WORKS IS COMPLETED • 5 UNITS IPS FLOORING WORKS BALANCE • 70% EXTERNAL STORM, SEWERAGE & WATER SUPPLY WORKS COMPLETED
TOWER C - 99% BRICK WORKS COMPLETED • 98% INTERNAL PLASTER WORKS COMPLETED • 98% EXTERNAL PLASTER WORKS COMPLETED • 6 UNITS IPS FLOORING WORKS IS BALANCE • 70% EXTERNAL STORM, SEWERAGE & WATER SUPPLY WORKS COMPLETED
TOWER D - 98% BRICK WORKS COMPLETED • 95% INTERNAL PLASTER WORKS COMPLETED • 95% EXTERNAL PLASTER WORKS COMPLETED • 9 UNITS IPS FLOORING WORKS IS BALANCE • 5% INTERNAL PUTTY/PAINTING WORKS COMPLETED • 80% EXTERNAL STORM, SEWERAGE & WATER SUPPL
TOWER E
TOWER F
TOWER G • IPS FLOORING COMPLETED EXCEPT 1 FLAT • 20% STONE/TILING WORKS COMPLETED • 5% INTERNAL PUTTY/PAINTING WORKS COMPLETED • 70% EXTERNAL STORM, SEWERAGE & WATER SUPPLY WORKS COMPLETED
EWS - 16 OUT OF 56 FLATS IPS FLOORING COMPLETED • 25% INTERNAL PUTTY/PAINTING WORKS COMPLETED • 20% EXTERNAL STORM, SEWERAGE & WATER SUPPLY WORKS COMPLETED
VILLAS 1-8 - 85% INTERNAL PUTTY/PAINTING WORKS COMPLETED • 85% INTERNAL WIRING WORKS COMPLETED • 90% EXTERNAL STORM, SEWERAGE & WATER SUPPLY WORKS COMPLETED
VILLAS 9-19 - 95% INTERNAL PLASTER WORKS COMPLETED • 50% EXTERNAL STORM, SEWERAGE & WATER SUPPLY WORKS COMPLETED