Park Elite Premium Construction Update Oct 2017

TOWER L - 95% STONE/TILING WORKS COMPLETED • 90% INTERNAL PUTTY/PAINTING WORKS COMPLETED • INTERNAL WIRING WORKS COMPLETED • LIFTS, FIRE-FIGHTING, EXTERNAL STORM, SEWERAGE & WATER SUPPLY WORKS COMPLETED
TOWER M - 95% STONE/TILING WORKS COMPLETED • 90% INTERNAL PUTTY/PAINTING WORKS COMPLETED • 90% INTERNAL WIRING WORKS COMPLETED • LIFTS, FIRE-FIGHTING, EXTERNAL STORM, SEWERAGE & WATER SUPPLY WORKS COMPLETED
TOWER N - 95% STONE/TILING WORKS COMPLETED • 85% INTERNAL PUTTY/PAINTING WORKS COMPLETED • 90% INTERNAL WIRING WORKS COMPLETED • 80% LIFTS WORKS COMPLETED • FIRE-FIGHTING, EXTERNAL STORM, SEWERAGE & WATER SUPPLY WORKS COMPLETED
TOWER H - 90% STONE/TILING WORKS COMPLETED • 50% INTERNAL PUTTY/PAINTING WORKS COMPLETED • 85% INTERNAL WIRING WORKS COMPLETED • 70% LIFTS WORKS COMPLETED • FIRE-FIGHTING, EXTERNAL STORM, SEWERAGE & WATER SUPPLY WORKS COMPLETED
TOWER J - 95% STONE/TILING WORKS COMPLETED • 85% INTERNAL PUTTY/PAINTING WORKS COMPLETED • 90% INTERNAL WIRING WORKS COMPLETED • LIFTS WORKS COMPLETED • FIRE-FIGHTING, EXTERNAL STORM, SEWERAGE & WATER SUPPLY WORKS COMPLETED
TOWER K - 95% STONE/TILING WORKS COMPLETED • 85% INTERNAL PUTTY/PAINTING WORKS COMPLETED • 90% INTERNAL WIRING WORKS COMPLETED • LIFTS WORKS COMPLETED • FIRE-FIGHTING, EXTERNAL STORM, SEWERAGE & WATER SUPPLY WORKS COMPLETED
TOWER A - 98% INTERNAL PLASTER WORKS COMPLETED • 51 OUT OF 60 FLATS IPS FLOORING COMPLETED • 20% LIFTS WORKS COMPLETED • 20% FIRE-FIGHTING WORKS COMPLETED • 70% EXTERNAL STORM, SEWERAGE & WATER SUPPLY WORKS COMPLETED
TOWER B - 99% BRICK WORKS COMPLETED • 98% INTERNAL PLASTER WORKS COMPLETED • 95% EXTERNAL PLASTER WORKS COMPLETED • 55 OUT OF 60 FLATS IPS FLOORING COMPLETED • 20% LIFTS WORKS COMPLETED • 20% FIRE-FIGHTING WORKS COMPLETED • 70% EXTERNAL STORM
TOWER C - 99% BRICK WORKS COMPLETED • 98% INTERNAL PLASTER WORKS COMPLETED • 98% EXTERNAL PLASTER WORKS COMPLETED • 54 OUT OF 60 FLATS IPS FLOORING COMPLETED • 20% LIFTS WORKS COMPLETED • 20% FIRE-FIGHTING WORKS COMPLETED • 70% EXTERNAL STORM
TOWER D - 98% BRICK WORKS COMPLETED • 95% INTERNAL PLASTER WORKS COMPLETED • 95% EXTERNAL PLASTER WORKS COMPLETED • 57 OUT OF 60 FLATS IPS FLOORING COMPLETED • 5% INTERNAL PUTTY/PAINTING WORKS COMPLETED • 20% LIFTS WORKS COMPLETED • 20% FIRE
TOWER E - IPS FLOORING COMPLETED • 5% INTERNAL PUTTY/PAINTING WORKS COMPLETED • 10% LIFTS WORKS COMPLETED • 30% FIRE-FIGHTING WORKS COMPLETED • 70% EXTERNAL STORM, SEWERAGE & WATER SUPPLY WORKS COMPLETED
TOWER F - IPS FLOORING COMPLETED • 5% INTERNAL PUTTY/PAINTING WORKS COMPLETED • 10% LIFTS WORKS COMPLETED • 30% FIRE-FIGHTING WORKS COMPLETED • 70% EXTERNAL STORM, SEWERAGE & WATER SUPPLY WORKS COMPLETED
TOWER G - IPS FLOORING COMPLETED EXCEPT 1 FLAT • 20% STONE/TILING WORKS COMPLETED • 5% INTERNAL PUTTY/PAINTING WORKS COMPLETED • 10% LIFTS WORKS COMPLETED • 30% FIRE-FIGHTING WORKS COMPLETED • 70% EXTERNAL STORM, SEWERAGE & WATER SUPPLY WORKS
EWS - 16 OUT OF 56 FLATS IPS FLOORING COMPLETED • 25% INTERNAL PUTTY/PAINTING WORKS COMPLETED • 20% EXTERNAL STORM, SEWERAGE & WATER SUPPLY WORKS COMPLETED
VILLAS 1-8 - IPS FLOORING COMPLETED • 85% INTERNAL PUTTY/PAINTING WORKS COMPLETED • 85% INTERNAL WIRING WORKS COMPLETED • 80% EXTERNAL STORM, SEWERAGE & WATER SUPPLY WORKS COMPLETED
VILLAS 9-19 - 95% INTERNAL PLASTER WORKS COMPLETED • IPS FLOORING COMPLETED • 50% EXTERNAL STORM, SEWERAGE & WATER SUPPLY WORKS COMPLETED