Park Generations Construction Update Aug 2017

PARK GENERATIONS
TOWER - 14 • STRUCTURE COMPLETED. • ALL BRICK WORKS COMPLETED. • FLATS RAILING WORKS COMPLETED. • INTERNAL PLASTER WORKS ALMOST COMPLETED. • 70% EXTERNAL PLASTER WORKS COMPLETED. • 36/75 FLATS IPS FLOORING COMPLETED. • DADO WORK IN 16 FLATS
TOWER - 15 • STRUCTURE COMPLETED. • ALL BRICK WORKS COMPLETED. • FLATS RAILING WORKS COMPLETED. • INTERNAL PLASTER WORKS ALMOST COMPLETED. • 70% EXTERNAL PLASTER WORKS COMPLETED. • 35/75 FLATS IPS FLOORING COMPLETED. • DADO WORK IN 20 FLATS
TOWER - 16 • STRUCTURE COMPLETED. • ALL BRICK WORKS COMPLETED. • FLATS RAILING WORKS COMPLETED. • INTERNAL PLASTER WORKS ALMOST COMPLETED. • 95% EXTERNAL PLASTER WORKS COMPLETED. • 95% IPS FLOORING COMPLETED. • DADO WORK IN 24 FLATS OUT OF 7
TOWER - 17 • INTERNAL PLASTER WORKS ALMOST COMPLETED. • 95% EXTERNAL PLASTER WORKS COMPLETED. • IPS FLOORING COMPLETED. • DADO WORK COMPLETED. • VITRIFIED FLOORING IN 48 FLATS OUT OF 75 COMPLETED. • TYP. LIFT LOBBY FLOORING & CLADDING WORKS IN
TOWER - 18 • STRUCTURE COMPLETED. • ALL BRICK WORKS COMPLETED. • FLATS RAILING WORKS COMPLETED. • INTERNAL PLASTER WORKS ALMOST COMPLETED. • 90% EXTERNAL PLASTER WORKS COMPLETED. • 70/75 FLAT IPS FLOORING COMPLETED. • DADO WORK IN 56 FLATS O
TOWER - 19 • INTERNAL PLASTER WORKS COMPLETED. • 95% EXTERNAL PLASTER WORKS COMPLETED. • IPS FLOORING COMPLETED. • DADO WORK COMPLETED. • VITRIFIED FLOORING COMPLETED. • TYP. LIFT LOBBY FLOORING & CLADDING WORKS IN PROGRESS. • PUTTY WORKS IN