Spacio Construction Update April 2018

TOWER-K • 85% BALCONY RAILING WORKS COMPLETED • 75% EXTERNAL PLASTER WORKS COMPLETED • 100% INTERNAL PLASTER WORKS COMPLETED • 11th FLOOR IPS FLOORING WORKS COMPLETED
TOWER-L • 80% BALCONY RAILING WORKS COMPLETED • 45% EXTERNAL PLASTER WORKS COMPLETED • 100% INTERNAL PLASTER WORKS COMPLETED • 2 FLOOR IPS FLOORING WORKS COMPLETED
TOWER-M • 20% BALCONY RAILING WORKS COMPLETED • 14th FLOORS INTERNAL PLASTER WORKS COMPLETED
TOWER-N • 80% BALCONY RAILING WORKS COMPLETED • 70% EXTERNAL PLASTER WORKS COMPLETED • 100% INTERNAL PLASTER WORKS COMPLETED • 3 rd FLOOR IPS FLOORING WORKS COMPLETED
TOWER-P • 60% BALCONY RAILING WORKS COMPLETED • 55% EXTERNAL PLASTER WORKS COMPLETED • 17th Floor INTERNAL PLASTER WORKS COMPLETED
TOWER-Q • 50% BALCONY RAILING WORKS COMPLETED • 35% EXTERNAL PLASTER WORKS COMPLETED • 100% INTERNAL PLASTER WORKS COMPLETED • 6 th FLOOR IPS FLOORING WORKS COMPLETED
TOWER- K REAR EXTERNAL PLASTER WORKS IN PROGRESS
MACHINE ROOM BOTTOM SLAB WORKS IN PROGRESS
SHAFT BRICKWORKS IN PROGRESS
PLUMBING WORKS IN PROGRESS
LANDSCAPING WORKS IN PROGRESS
SWIMMING POOL WORKS IN PROGRESS
37 D CLUB & SWIMMING POOL WORKS IN PROGRESS
TOWER N - SAMPLE FLAT
TOWER N - SAMPLE FLAT
TOWER N - SAMPLE FLAT