Spacio Construction Update Dec 2017

TOWER-K - 95% RAILING WORKS COMPLETED. • EXTERNAL PLASTER WORKS IN PROGRESS • 16TH FLOOR INTERNAL PLASTER WORKS COMPLETED, 17TH FLOOR WORKS IN PROGRESS. • 8 TH FLOOR IPS FLOORING WORKS COMPLETED.
TOWER-L - BRICK WORKS COMPLETED. • 80% RAILING WORKS COMPLETED. • EXTERNAL PLASTER WORKS IN PROGRESS. • 16TH FLOOR INTERNAL PLASTER WORKS COMPLETED, 17TH FLOOR WORKS IN PROGRESS.
TOWER-M - GROUND TO 12TH FLOOR BRICK WORKS COMPLETED, 13TH FLOOR BRICK WORKS IN PROGRESS. • 12TH FLOOR INTERNAL PLASTER WORKS COMPLETED.
TOWER-N - 90% RAILING WORKS COMPLETED. • 19TH FLOOR INTERNAL PLASTER WORKS COMPLETED. • EXTERNAL PLASTER WORKS IN PROGRESS.
TOWER-P - 80% RAILING WORKS COMPLETED. • 15TH FLOOR INTERNAL PLASTER WORKS COMPLETED, 16TH FLOOR INTERNAL PLASTER WORKS IN PROGRESS.
TOWER-Q - 85% BALCONY RAILING WORKS COMPLETED. • 16TH FLOOR INTERNAL PLASTER WORKS COMPLETED, 17TH FLOOR INTERNAL PLASTER WORKS IN PROGRESS. • EXTERNAL PLASTER WORKS IN PROGRESS.
SAMPLE FLAT
SAMPLE FLAT
SAMPLE FLAT
SAMPLE FLAT
SAMPLE FLAT
SAMPLE FLAT