Discovery Park Construction Update November 2018

TOWER – K OC RECEIVED
TOWER – J OC RECEIVED
TOWER – H OC RECEIVED
TOWER – G OC RECEIVED
TOWER – F OC RECEIVED
TOWER - L 12TH FLOOR SLAB WORKS COMPLETED. 1 ST TO 11TH FLOOR BRICK WORKS COMPLETED.
TOWER - M 13TH FLOOR SLAB CASTED. 1 ST TO 11TH FLOOR BRICK WORKS COMPLETED.
TOWER - A • TERRACE SLAB CASTED • GROUND TO 14TH FLOOR BRICK WORKS COMPLETED • 285/300 RAILING WORKS COMPLETED • 78/88 FLATS INTERNAL PLASTER WORKS COMPLETED • 80% EXTERNAL PLASTER WORKS COMPLETED • 24/88 FLATS IPS FLOORING WORKS COMPLETED • STONE FIXING WORKS IN PROGRESS
TOWER - B • TERRACE SLAB CASTED • 1 ST TO 18TH FLOOR BRICK WORKS COMPLETED • 305/532 RAILING WORKS COMPLETED • 136/142 FLATS INTERNAL PLASTER WORKS COMPLETED • 70% EXTERNAL PLASTER WORKS COMPLETED • STONE FIXING WORKS IN PROGRESS
CLUB BLOCK WORKS IN PROGRESS
KIDS PLAY AREA
OPEN GYM
LANDSCAPING WORKS IN PROGRESS
SWIMMING POOL WORKS IN PROGRESS