In order to give you a better experience, we are renovating our website. However, please note that the data mentioned on the website is still being updated. For accurate and upto date information, please contact our team at customercare@bptp.com.
In order to give you a better experience, we are renovating our website. However, please note that the data mentioned on the website is still being updated. For accurate and upto date information, please contact our team at customercare@bptp.com.
Slideshow Image 1

Park Elite Premium Construction Update November 2018

FRONT ELEVATION
TOWER- A • 80% TERRACING WORKS COMPLETED. • 59/60 UNITS IPS FLOORING WORKS COMPLETED. • 80% STONE & TILES WORKS COMPLETED. • 20% INTERNAL PUTTY AND PAINT WORKS COMPLETED. • 30% INTERNAL WIRING WORKS COMPLETED. • 60% LIFT WORKS COMPLETED. • 60% FIRE FIGHTING WORKS COMPLETED. • 80% EXTERNAL STORM, SEWERAGE & WATER SUPPLY WORKS COMPLETED.
TOWER- B • 36/40 UNITS IPS FLOORING WORKS COMPLETED. • 60% STONE & TILES WORKS COMPLETED. • 10% INTERNAL PUTTY AND PAINT WORKS COMPLETED. • 30% INTERNAL WIRING WORKS COMPLETED. • 60% LIFT WORKS COMPLETED. • 60% FIRE FIGHTING WORKS COMPLETED. • 80% EXTERNAL STORM, SEWERAGE & WATER SUPPLY WORKS COMPLETED.
TOWER- C • 95% EXTERNAL PLASTER WORKS COMPLETED. • 5% INTERNAL PUTTY/PAINT WORKS COMPLETED. • 40% STONE & TILES WORKS COMPLETED. • 100% IPS FLOORING WORKS COMPLETED. • 30% LIFT WORKS COMPLETED. • 50% FIRE FIGHTING WORKS COMPLETED. • 80% EXTERNAL STORM, SEWERAGE & WATER SUPPLY WORKS COMPLETED.
TOWER- D • 98% EXTERNAL PLASTER WORKS COMPLETED. • 38/40 UNITS IPS FLOORING WORKS COMPLETED. • 60% STONE & TILES WORKS COMPLETED. • 5% INTERNAL PUTTY AND PAINT WORKS COMPLETED. • 50% FIRE FIGHTING WORKS • 60% LIFT WORKS COMPLETED. • 80% EXTERNAL STORM, SEWERAGE & WATER SUPPLY WORKS COMPLETED.
TOWER- G • 100% EXTERNAL PLASTER WORKS COMPLETED. • 55% STONE & TILES WORKS COMPLETED. • 100% IPS FLOORING WORKS COMPLETED. • 30% INTERNAL WIRING WORKS COMPLETED. • 10% INTERNAL PUTTY/PAINT WORKS COMPLETED. • 10% LIFT WORKS COMPLETED. • 60% FIRE FIGHTING WORKS COMPLETED. • 80% EXTERNAL STORM, SEWERAGE & WATER SUPPLY WORKS COMPLETED.
TOWER- J • 100% EXTERNAL PLASTER WORKS COMPLETED. • 50% STONE & TILES WORKS COMPLETED. • 100% IPS FLOORING WORKS COMPLETED. • 20% INTERNAL WIRING WORKS COMPLETED. • 10% INTERNAL PUTTY/PAINT WORKS COMPLETED. • 10% LIFT WORKS COMPLETED. • 60% FIRE FIGHTING WORKS COMPLETED. • 80% EXTERNAL STORM, SEWERAGE & WATER SUPPLY WORKS COMPLETED.
TOWER- K • 100% EXTERNAL PLASTER WORKS COMPLETED. • 100% IPS FLOORING WORKS COMPLETED. • 50% STONE & TILES WORKS COMPLETED. • 10% INTERNAL PUTTY/PAINT WORKS COMPLETED. • 20% INTERNAL WIRING WORKS COMPLETED. • 10% LIFT WORKS COMPLETED. • 50% FIRE FIGHTING WORKS COMPLETED. • 80% EXTERNAL STORM, SEWERAGE & WATER SUPPLY WORKS COMPLETED.
EWS TOWER • 100% EXTERNAL PLASTER WORKS COMPLETED. • 56/56 UNITS IPS FLOORING WORKS COMPLETED. • 25% INTERNAL PUTTY/PAINT WORKS COMPLETED. • 60% FIRE FIGHTING WORKS COMPLETED. • 80% EXTERNAL STORM, SEWERAGE & WATER SUPPLY WORKS COMPLETED.
VILLAS 10-19 • 95% INTERNAL PLASTER WORKS COMPLETED. • 100% EXTERNAL PLASTER WORKS COMPLETED. • 100% IPS FLOORING WORKS COMPLETED. • 30% STONE & TILES WORKS COMPLETED. • 80% EXTERNAL STORM, SEWERAGE & WATER SUPPLY WORKS COMPLETED.
GREEN SCAPING WORKS AT EXTERNAL PARKING
GAZIBO AT CENTRAL PLAZA
STONE WORKS IN PROGRESS AT VILLAS