Amstoria Construction Update February 2019

A-106 TO 110 - HORTICULTURE WORKS IN PROGRESS
A155 TO 160 - EXTERNAL TEXTURE PAINT WORKS COMPLETED
A166 TO A170 EXTERNAL PLASTER WORKS IN PROGRESS
D124 & 125 - OC EXPECTED SHORTLY
D136 TO 138 - EXPECTED SHORTLY
D139 TO 143 - EXTERNAL PAINTING WORKS IN PROGRESS
D146 TO 148 - EXTERNAL TEXTURE PAINTING WORKS IN PROGRESS
D136 TO 138 & D 139 TO 143 - ROAD AND PARKING WORKS IN PROGRESS
A 121 SECOND FLOOR ROOF CASTED