Park Generations Construction Update March 2019

TOWER - 1 OC RECEIVED
TOWER - 2 OC RECEIVED
TOWER - 3 OC RECEIVED
TOWER - 4 • 95% EXTERNAL PLASTER COMPLETED • IPS FLOORING WORKS COMPLETED • 75/75 FLATS DADO WORKS COMPLETED • 73/75 FLATS VITRIFIED TILES FLOORING WORKS COMPLETED • 1 ST TO 19TH FLOOR INTERNAL PUTTY WORK COMPLETED • EXTERNAL PAINT & PUTTY WORKS IN PROGRESS
TOWER - 5 • EXTERNAL PLASTER COMPLETED • 74/75 FLATS IPS FLOORING WORKS COMPLETED • 75/75 FLATS DADO WORKS COMPLETED • 75/75 FLATS VITRIFIED TILES FLOORING WORKS COMPLETED • GROUND TO 19TH FLOOR INTERNAL PUTTY WORK COMPLETED • EXTERNAL PAINT & PUTTY WORKS IN PROGRESS • LIFT LOBBY CLADDING WORKS IN PROGRESS
TOWER - 6 • EXTERNAL PLASTER COMPLETED • 74/75 FLATS IPS FLOORING WORKS COMPLETED • 75/75 FLATS DADO WORKS COMPLETED • 75/75 FLATS VITRIFIED TILES FLOORING WORKS COMPLETED • 1 ST TO 19TH FLOOR INTERNAL PUTTY WORK COMPLETED • EXTERNAL PAINT & PUTTY WORKS IN PROGRESS • LIFT LOBBY FLOORING WORKS COMPLETED
TOWER 1 ENTRANCE
TOWER 2 ENTRANCE
TOWER 3 ENTRANCE
ARCHITECTURE FEATURE AT PODIUM
GREENERY AT PODIUM
PARKING AREA
FIRE-TENDER PATH
HORTICULTURE WORKS AT GROUND FLOOR
KIDS PLAY AREA
WATER BODY
TOWER-1 ENTRANCE