Park Generations Construction Update Sep 2018

TOWER - 1 COMPLETED
TOWER - 2 • PUTTY WORKS COMPLETED PAINTING WORKS IN PROGRESS • 95% EXTERNAL PUTTY & TEXTURE WORKS COMPLETED
TOWER - 3 • PUTTY WORKS COMPLETED PAINTING WORKS IN PROGRESS • 90% EXTERNAL PUTTY & TEXTURE WORKS COMPLETED
TOWER - 4 • 95% EXTERNAL PLASTER COMPLETED • IPS FLOORING WORKS COMPLETED • 74/75 FLATS DADO WORKS COMPLETED • 65/75 FLATS VITRIFIED TILES FLOORING WORKS COMPLETED • 1 ST TO 17TH FLOOR SINGLE COAT INTERNAL PUTTY WORK COMPLETED • EXTERNAL PAINT & PUTTY WORKS IN PROGRESS
TOWER - 5 • 100% EXTERNAL PLASTER COMPLETED • 74/75 FLATS IPS FLOORING WORKS COMPLETED • 74/75 FLATS DADO WORKS COMPLETED • 74/75 FLATS VITRIFIED TILES FLOORING WORKS COMPLETED • 2 ND TO 13TH FLOOR SINGLE COAT INTERNAL PUTTY WORK COMPLETED • EXTERNAL PAINT & PUTTY WORKS IN PROGRESS
TOWER - 6 • INTERNAL PLASTER WORKS IN PROGRESS • EXTERNAL PLASTER COMPLETED • 74/75 FLATS IPS FLOORING WORKS COMPLETED • 74/75 FLATS DADO WORKS COMPLETED • 74/75 FLATS VITRIFIED TILES FLOORING WORKS COMPLETED • 1 ST TO 19TH FLOOR SINGLE COAT INTERNAL PUTTY WORK COMPLETED • EXTERNAL PAINT & PUTTY WORKS IN PROGRESS
TOWER - 2 MAIN ENTERANCE LOBBY
TOWER - 1 MAIN ENTRY
FTP IN FRONT OF TOWER - 1
FEATURE WALL IN FRONT OF TOWER - 1
GREEN PODIUM IN FRONT OF TOWER - 1, 2 & 3
WATER BODY
TRANSFORMER YARD
LANDSCAPING WORKS IN PROGRESS