Spacio Construction Update August 2019

TOWER-K • 95% BALCONY RAILING WORKS COMPLETED • 95% EXTERNAL PLASTER WORKS COMPLETED • 100% INTERNAL PLASTER WORKS COMPLETED • 19th FLOOR IPS FLOORING WORKS COMPLETED • 16th FLOOR TILES/STONE FIXING WORKS COMPLETED • PUTTY/PAINT WORKS IN PROGRESS
TOWER-L • 95% BALCONY RAILING WORKS COMPLETED • 95% EXTERNAL PLASTER WORKS COMPLETED • 19TH FLOOR IPS FLOORING WORKS COMPLETED • 14TH FLOOR TILES/STONE FIXING WORKS COMPLETED • PUTTY/PAINT WORKS IN PROGRESS
TOWER-M • 60% BALCONY RAILING WORKS COMPLETED • 95% EXTERNAL PLASTER WORKS COMPLETED • 19TH FLOOR IPS FLOORING WORKS COMPLETED
TOWER-N • 95% BALCONY RAILING WORKS COMPLETED • 95% EXTERNAL PLASTER WORKS COMPLETED • 19TH FLOOR IPS FLOORING WORKS COMPLETED • 18th FLOOR TILES/STONE FIXING WORKS COMPLETED • PUTTY/PAINT WORKS IN PROGRESS
TOWER-P • 95% BALCONY RAILING WORKS COMPLETED • 95% EXTERNAL PLASTER WORKS COMPLETED • 100% INTERNAL PLASTER WORKS COMPLETED • 17TH FLOORS IPS FLOORING WORKS COMPLETED • TILES/STONE FIXING WORKS IN PROGRESS
TOWER-Q • 95% BALCONY RAILING WORKS COMPLETED • 85% EXTERNAL PLASTER WORKS COMPLETED • 19TH FLOOR IPS FLOORING WORKS COMPLETED
PUTTY WORKS IN PROGRESS
SKIRTING FIXING WORKS IN PROGRESS
BALCONY STONE FIXING WORKS IN PROGRESS
TILES FIXING WORKS IN PROGRESS
DOOR FRAME FIXING WORKS IN PROGRESS
HORTICULTURE WORKS IN PROGRESS
HORTICULTURE WORKS IN PROGRESS